Ram River Bridge

  • Client Name: West Fraser
  • Project Name: Ram River Bridge
  • Location: Rocky Mountain House, Alberta
  • Sector: Forestry
  • Timeline Start: August 31, 2021
  • Timeline End: August 14, 2022

Construction of new bridge over the Ram River in Rocky Mtn House, AB. Installation and supply of 5 bridge spans, Including piling,

  • Piling
  • Cutoff / prep / weld plates as close to ground level as possible
  • Install above ground pile assemblies / caps
  • Install bridge sections
  • Install deck modules
  • Install End-fill materials at abutments