Masset Bridge and Culvert

  • Client Name: Department of Defense | SNC Lavalin
  • Project Name: Masset Bridge and Culvert
  • Location: Masset, BC
  • Sector: Government
  • Timeline Start: June 27, 2021
  • Timeline End: May 29, 2021

Formula was awarded the Masset Bridge/Culvert with SNC Lavalin for the National Defense. The scope of work included:

Bridge

  • Remove existing timber bridge
  • Prepare site for construction of new bridge
  • Supply/ Install new piles
  • Supply/ Install new reinforced concrete pile caps with wing walls
  • Earthworks for embankment slop and installation of rip-rap
  • Upgrade existing approaches
  • Erect ACROW 200 Series Bridge
  • Supply/ Install timber deck, curbs, and beam

Culvert

  • Earthworks to prepare site for new culvert
  • Removal of existing culvert
  • Supply/Install new culvert