View Projects

Sverzac Bridge Replacement

Client Name
Argo Road Maintenance
Location
Dawson Creek, BC
Sector
Forestry
Started
2021
Completed
2021
Cost
$535,000.00

Project Summary

Formula was hired to replace the Sverzac Bridge near Dawson Creek, BC. The scope of work for this bridge included:

  • Removal of existing debris in and around existing bridge
  • Removal of existing bridge including timber sub-structure
  • Supply and installation of lock block foundations c/w timber sills, lock block return walls and timber ballast boards
  • Supply and installation of (1) 60’ L100 oil field portable with timber deck mods (21’ travelled width)
  • Supply and installation of 200 cu.m of 50kg rip rap with geotextile fabric
  • Supply and Installation of 400 cu.m of 1” crush as bridge end fill

Project Gallery