Portal Intake

  • Client Name: Peace River Hydro Partners
  • Project Name: Portal Intake
  • Location: Fort St. John, BC
  • Sector: TBD
  • Timeline Start: December 31, 2017
  • Timeline End: December 31, 2018

The supply and installation of 25 – 914mm dia. X 19.05mm wt., steel pipe pile casings by means of driving and drilling c/w steel reinforcement cages and infilling with concrete. Casings vary in lengths from 19.64m to 26.88m. All casings are to be embedded a minimum of 10m into underlying bedrock.

Throughout the project crews were challenged by the winter conditions in northern BC and a tight schedule.