Nicomen Creek – Flood Restoration Works (Emergency)

  • Client Name: BC Ministry of Forests & Ministry of Transportation & Infrastructure
  • Project Name: Nicomen Creek #1 Highway and Nicomen Nation Road
  • Location: Nicomen, BC
  • Sector: TBD
  • Timeline Start: October 31, 2021
  • Timeline End: June 30, 2022

Formula completed the emergency works for the Nicomen section of Highway #1 after the impact from BC’s atmospheric river.

Scope included:

  • Demolition and removal of a 24-meter steel girder concrete precast deck bridge founded on spread footings
  • Installation of a replacement 36-meter steel girder bridge deck with modular deck panels founded on piling on Nicomen Nation Road
  • Preservation of a triple span steel girder bridge founded on concrete pier columns; included installation of temporary supports for one main pier column which was undermined
  • Construction of tote roads
  • Design and install temporary structural works to shore up bridge, restore pier column foundation and jack bridge spans back into original orientation.