Brule 69km & 230kv Substations

  • Client Name: Walter Energy
  • Project Name: Brule 69km & 230kv Substations
  • Location: Chetwynd, BC
  • Timeline Start: December 31, 2010
  • Timeline End: December 30, 2011

Site Grading Preparation
Prepare and level the site to the required specifications, ensuring proper drainage and stability for construction activities.

Excavation Work
Perform excavation to the specified depth for foundations, ensuring accuracy according to the project design and soil conditions.

Foundation Footings
Construct foundation footings, ensuring the correct dimensions and reinforcement to support the structure as per design requirements.

Concrete Supply and Placement
Pour and finish concrete for footings, foundations, and other structural components, ensuring adherence to strength and durability standards.

Rebar Installation
Install reinforcing steel (rebar) in accordance with structural drawings to provide additional strength and support to concrete elements.